How do you incorporate feedback from stakeholders into your Sprint?

During the Sprint:

  • Feedback is captured but doesn’t change the current Sprint scope.
  • Product Owner logs feedback in the Product Backlog.
  • Team might discuss it in refinement sessions or plan to act on it in the next Sprint.

Follow On:

During Sprint Review:

  • Stakeholders review the Increment.
  • Discuss what’s useful, missing, or needs improvement.
  • PO adjusts priorities accordingly.

Example:

After a demo, a stakeholder suggests a visual improvement to a dashboard. The team

doesn't implement it immediately but adds it to the backlog and addresses it in the next

Sprint.